Which step in the change management process comes immediately after the impact assessment?

Explanation:
The step after evaluating the potential effects of a proposed change is to obtain authorization to proceed. The impact assessment collects details on risk, dependencies, resources, and back-out plans so decision-makers can judge whether the change is acceptable to implement. With that information, the Change Authority (such as the CAB or designated manager) approves or rejects the change. Once approved, work moves forward into planning, testing, and deployment. The request comes before the assessment, and testing occurs after approval and planning, so approval is the natural next step.

The step after evaluating the potential effects of a proposed change is to obtain authorization to proceed. The impact assessment collects details on risk, dependencies, resources, and back-out plans so decision-makers can judge whether the change is acceptable to implement. With that information, the Change Authority (such as the CAB or designated manager) approves or rejects the change. Once approved, work moves forward into planning, testing, and deployment. The request comes before the assessment, and testing occurs after approval and planning, so approval is the natural next step.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy